Surface preparation :
-
1The substrate, substrate preparation and product application must comply with the latest French unified codes of building practice 59.1.
-
2Apply the product to a clean, dust-free, grease-free and dry surface.
-
3To remove traces of efflorescence, laitance or grout film, use Guard Cleaner® Surface Preparation.
-
4To remove grease stains, use Guard Cleaner® Maintenance.
-
5Rinse carefully until the surface is free of any trace of cleaner.
-
6Wait for complete drying through, approximately 24 hours before treatment.
Application :
- Shake the package well before use in order to fully homogenise the pigments with the rest of the composition. Use an electric stirrer.
- Carry out a preliminary test.
Application with HVLP :
- Apply from the bottom up in at least 2 cross coats.
- Do not exceed the recommended final consumption of 120 to 160 g/m2.
- Do not overload.
- Drying time between each coat: 15 to 60 minutes depending on weather conditions.
- The 1st coat must be dry to the touch before applying the 2nd coat.
- Protected drying: 24 hours
- Optimum effectiveness obtained after 7 days.
Application with roller (only used for non-textured smooth surfaces):
- Apply from the bottom up in at least 2 cross coats.
- Do not exceed the recommended final consumption of 120 to 160 g/m2.
- Do not overload.
- Drying time between each coat: 15 to 60 minutes depending on weather conditions.
- The 1st coat must be dry to the touch before applying the 2nd coat.
- Protected drying: 24 hours
- Optimum effectiveness obtained after 7 days.
For further information, refer to the data sheet and safety sheet.
-